Key takeaways
- Classify spares: critical (long lead, stops production), consumable, and general stock.
- Set min/max or reorder points from actual consumption, not guesswork.
- Issue parts against work orders so cost per asset is real.
- Review slow-moving and obsolete stock at least twice a year.
The two failure modes
Too little stock and a two-hour repair becomes a two-week wait. Too much and capital sits on shelves, parts go obsolete, and nobody knows what is there.
Classify your spares
- Critical / insurance spares — long lead time, needed for A-critical assets. Hold even if rarely used.
- Consumables — filters, belts, lubricants. Reorder from consumption.
- General stock — fasteners, fittings. Bulk, low value.
Reorder points
Reorder point = (average daily usage × lead time in days) + safety stock. Recalculate when usage or suppliers change.
Link parts to work orders
Issuing parts against the job tells you the true cost per asset, flags assets eating spares, and keeps stock counts honest.
How Opmaint helps
Opmaint tracks stock by location, alerts on reorder points and deducts parts when technicians close a work order. See parts and inventory.
Frequently asked questions
What is a critical spare?
A part whose absence would extend an outage on a critical asset, usually because it has a long lead time or is hard to source.