Key takeaways
- PM compliance = PMs completed on time ÷ PMs scheduled × 100.
- Define the grace window (e.g. ±10% of the interval) and stick to it.
- Low compliance usually means too many PMs, unclear tasks or no time protected for planned work.
- Track it per asset criticality and per technician.
The calculation
If 180 PMs were due this month and 162 were completed within their window, PM compliance is 162 ÷ 180 = 90%.
Why it slips
- Breakdowns pull technicians off planned work.
- PM lists copied from manuals without trimming.
- Paper schedules nobody checks.
- Tasks too vague to finish confidently.
How to raise it
- Cut or merge low-value PMs.
- Protect planned-work time on the weekly schedule.
- Prioritise PMs on critical assets first.
- Write PMs as short, checkable checklists.
- Review missed PMs every week, not every quarter.
How Opmaint helps
Opmaint creates PM work orders automatically and reports compliance by asset, team and technician, so slipping schedules show up the week they slip.
Frequently asked questions
What is a good PM compliance percentage?
90% or higher is a common target. Below 80% usually means the preventive program is not keeping up.