Key takeaways
- OEE = Availability × Performance × Quality.
- Availability losses are mostly breakdowns and changeovers — maintenance territory.
- Track OEE per asset or line, not just plant-wide.
- Use the six big losses to find where OEE is going.
The formula
- Availability = run time ÷ planned production time
- Performance = (ideal cycle time × total count) ÷ run time
- Quality = good count ÷ total count
Example: 90% availability × 95% performance × 98% quality = 83.8% OEE.
The six big losses
- Breakdowns
- Setup and adjustments
- Small stops
- Reduced speed
- Startup rejects
- Production rejects
The first two hit availability, the middle two performance, the last two quality.
Where maintenance moves OEE
Fewer breakdowns (better PMs, higher MTBF) and faster recovery (lower MTTR) raise availability directly. Well-maintained machines also hold speed and produce fewer rejects.
How Opmaint helps
Opmaint records downtime against each asset from breakdown work orders, giving you the availability side of OEE and the failure history behind it.
Frequently asked questions
What is a world-class OEE?
85% is often quoted as a world-class benchmark for discrete manufacturing, though realistic targets depend on the process.