Key results
- Four branches live, the first since August 2025.
- JRR U2 has closed 9,741 work orders at a 99% completion rate.
- About 650 completed work orders a month at JRR U2 for 15 months, with only 5 ever skipped.
- 229 recurring PM schedules and 125 checklist templates at JRR U2.
At a glance
Four branches live, the first since August 2025. Every number in this section is for the largest, JRR U2, read off the live account during demos on Oct 16 and Nov 5, 2026.
| Customer | Jain Metal Group, metal recycling, Chennai; four branches live (JRR U2, JRR U1, JGT U1, JGT U3); JRR U2 shown here |
| Operations on site | Smelting, refining, copper wire drawing, battery breaking (BBSU), dispatch |
| Assets in Opmaint | 694, from 10-ton rotary furnaces to forklifts and DG sets |
| Locations | 42 |
| Users | 50, across 9 teams |
| Checklist templates | 125 |
| Recurring PM schedules | 229 |
| Spare parts catalogued | 2,401 |
| Work orders completed | 9,567 (99% completion rate) |
| Modules in daily use | Requests, work orders, PM schedules, checklists, asset history, per-user performance |
Across all four branches
Across four branches, Jain Metal Group has completed 13,294 work orders in Opmaint, about 98% of the 13,594 raised, on 1,436 assets with 118 users.
| Branch | First work order | Users | Assets | Work orders raised | Completed | Completion | Recurring PMs | Checklists | Meters |
|---|---|---|---|---|---|---|---|---|---|
| JRR U2 | Aug 14, 2025 | 50 | 694 | 9,814 | 9,741 | 99% | 204 | 126 | 30 |
| JRR U1 | Sep 24, 2025 | 38 | 542 | 2,532 | 2,332 | 92% | 121 | 24 | 23 |
| JGT U1 | Sep 24, 2025 | 14 | 135 | 1,172 | 1,151 | 96% | 48 | 34 | 10 |
| JGT U3 | Sep 10, 2026 | 16 | 65 | 76 | 70 | 91% | 21 | 29 | 5 |
| Total | 118 | 1,436 | 13,594 | 13,294 | 98% | 394 | 213 | 68 |
Read from the live account on Nov 13, 2026; completion is completed over raised. Each branch also keeps its own parts catalogue of roughly 2,400 items (JGT U1 has 9,882), not summed because the lists likely overlap.
Two things stand out:
The plant
JRR Unit 2 runs equipment that cannot be allowed to stop: rotary and pot furnaces, ingot casting machines, ladles, air pollution control units, cooling towers, EOT cranes, five diesel generators and a fleet of battery and diesel forklifts. Assets are tagged by criticality, with the furnaces and DG sets marked Super Critical.
Before Opmaint, maintenance across the group ran on paper and Excel. Now the whole plant is in Opmaint, not just the maintenance team. Production people raise problems; maintenance fixes them; supervisors approve and watch.
| Role in Opmaint | Who | What they do |
|---|---|---|
| Requester | Operators in smelting, refining, copper, BBSU, dispatch | Report breakdowns from the floor with a photo |
| Limited user | Electrical and mechanical technicians | Receive work orders, fill checklists, close jobs |
| Full user | Maintenance supervisors | Approve requests, assign work, watch progress |
| Admin | Plant maintenance head | Set up schedules, checklists and teams |
The nine teams are Dispatch, Quality, Copper, BBSU, Production-VDF, Refining, Smelting, Maintenance-Electrical (5 people) and Maintenance-Mechanical (4 people). Most of the 50 users are requesters, which is the point: the people who see a problem first can log it.
How a breakdown moves
At JRR U2 a breakdown is a request first and a work order second, so nothing reaches a technician without a supervisor seeing it.
A real example from Oct 16: at 7:56 AM an operator in Refining logged "Shed-E cooling tower motor is tripped" with a photo of the motor, marked High priority. It sat in the supervisor's approval queue alongside 14 other pending requests and 15 approved ones. Approving it with the plant's saved "Furnace maintenance" workflow assigns the electrical and mechanical technicians, adds the right watchers and attaches the breakdown checklist in one step.
The record that builds up is the useful part. Rotary Furnace 8, a 10-ton Super Critical furnace, shows 41 completed work orders and 27 breakdowns in its history, each with what failed and how long the fix took. Its latest, a PH unit oil leak on Oct 14, was closed in 5 hours 17 minutes.
Requests: the feature they lean on most
Jain Metal's operators have raised 4,383 maintenance requests in Opmaint across the four branches, so the people who see a fault first are the ones who log it.
| Branch | Requests raised |
|---|---|
| JRR U2 | 2,781 |
| JRR U1 | 999 |
| JGT U1 | 567 |
| JGT U3 | 36 |
| Total | 4,383 |
Read from the live account on Nov 13, 2026.
A request is how a breakdown enters the system. An operator on the floor, usually on the free requester role, logs the fault from a phone with a photo and a priority. It lands in a Pending column for a supervisor, moves to Approved when a technician is assigned, and to Completed when the work is done. The titles read like the floor talks: "Wheel loader diesel filter leakage", "Plug crushers: motor belt need to fix", "Shed-E cooling tower motor is tripped".
Before Opmaint, these faults were tracked on paper and Excel. At JRR U2, 2,781 requests over 15 months is about six a day, each one with a time, a photo and a name on it.
Preventive maintenance and checklists
Most of the plant's maintenance is planned, not reactive: 229 recurring schedules generate the work, and 468 PM work orders were already projected for November when we looked on Oct 16.
| Cadence | What runs on it at JRR U2 |
|---|---|
| Daily | DG set registers, air compressor registers |
| Monthly | Rotary and pot furnaces, ingot casting machines, APCM hoods, EOT cranes, forklifts, APFC panels, cooling towers, lathes, welding and crushing machines |
| Yearly | AMC renewals for DG sets and compressors, Rule 30 inspection, CTPT/ABT meter calibration |
Each job carries its own checklist. The daily air compressor register has 14 checks, such as outlet air pressure and oil separator level; a check marked Not OK takes a comment and a photo. The DG register ends with a "Done by" field and a signature before it can be submitted. Every closed job produces a numbered PDF report (format JR/GU/2026-27/GU-9335) with start, due and completion times.
The plant has built 125 checklist templates, covering motor predictive maintenance, electrical compliance and AMC, air conditioners, weighing scales, a breakdown checklist and a CAPA report.
Supervisors also use per-person views. A technician's page shows pending, completed and overdue work for the month and an on-time flag on every job, so missed PMs show up against a name, not just a total.
Results so far
JRR U2 completed 372 work orders in the 20 days between our two snapshots, about 19 a day, and held a 99% completion rate throughout.
| Measure | Oct 16, 2026 | Nov 5, 2026 |
|---|---|---|
| Work orders completed (all time) | 9,195 | 9,567 |
| Completion rate | 99% | 99% |
| Pending work orders | 50 | 66 |
| Overdue work orders | 27 | 34 |
| Open requests | 16 | 2 |
| Assets | 692 | 694 |
Overdue work is small but real: 34 of roughly 9,650 work orders. October alone had 349 work orders raised by mid-month, 304 of them already done.
What comes next
The plant runs work orders, PMs and checklists fully, but two modules are loaded and barely used, and they are exactly where Opmaint is different.